Geoprint for Energy Club Connections and Operations (GECCO)
| Funding mechanism | Network Innovation Allowance (NIA) |
|---|---|
| Duration | Feb 2026 - Apr 2027 |
| Estimated expenditure | £609,471 |
| Research area | Net zero and the energy system transition |
Project partner: TNEI, Regen, Energy Local, Hook Norton
Overview
Geoprint for Energy Club Connections and Operations (GECCO) will explore a new type of flexible connection providing a fairer, smarter way for community energy groups to connect. It will develop and test a “geoprint” approach to identify optimal points for linking local generation and demand collectively, reducing connection costs and supporting community energy operations. The project aims to unlock long-term benefits for communities by enabling local balancing, lower bills, and creating a scalable, regulatorily viable connection framework for community-led energy models.
Problem(s)
Community energy is seen as a key part of a just net zero transition by key stakeholders including GB Energy, however, it has not reached its full potential because:
- Community energy groups struggle to connect. They use their limited time and money only to find that a connection is not economically viable due to network constraints.
- Community energy groups struggle to find long-term financial mechanisms to support their projects. There is an opportunity for more of the economic value from generation projects to be retained locally if modification P441 to the Elexon and Balancing and Settlement Code progresses (enables local energy trading at a complex site).
Method(s)
The project will seek to develop and test a connection for a ‘Geoprint’ of demand and generation and in doing so will provide new insights into NGED modelling practices as well as how community energy is treated within NGED.
This is achieved by;
- the selection of three community energy groups,
- investigating how a Geoprint connection offer could be applied at these locations,
- considering the regulatory implications and challenges which could be associated with a Geoprint connection available exclusively to community energy groups.
- After a stage gate, the project then considers the practical implications of the Geoprint connection, for example, how it would change the standard connection journey,
- the last investigation within the project considers placing the Geoprint in the context of scenarios including DFES.
- Lastly, the learnings from the project will be disseminated as well as considering the next steps.
Work Package 1 – Landscape and Data
Two community energy case studies will be selected in addition to project partner Hook Norton giving three case studies in total. During WP1, these community groups will be interviewed to understand their development ambitions. This will be used to inform the design of the Geoprint at each location.
Success criteria:
- Initial hypothesis of the cost benefits to a customer and to the grid for a customer connecting a Geoprint.
- Two community energy groups identified and case study analysis completed of them and Hook Norton.
- NGED modelling assumptions and data required for project identified.
Work Package 2A – Geoprint Design and Technical Assessment
At the three case study sites, TNEI will run technical feasibility assessments to develop the connection options which could be given to these community energy groups based on the ambitions identified in WP1.
Success criteria:
- Create the methodology for the Geoprint connection.
- Determine the technical feasibility of the Geoprint Connection.
- Identify improvements for NGED modelling assumptions and opportunities to apply monitoring.
- Determine for each case study, the associated costs of developing their ambition using standard connections or the Geoprint connection.
Work Package 2B – Regulatory and Commercial
This work package will look at the regulatory implications for the Geoprint connection in the context of local energy markets and assess the potential commercial arrangements.
Success criteria:
- Interviews with wider industry to obtain full regulatory landscape across Elexon, DNO’s, suppliers, government etc.
- Understand detailed connection policies and implications for new types of connection.
- Develop proposals for regulatory amendments and drive momentum in discussions of change.
- Define commercial models for applying Energy Clubs and accelerating adoption of local energy markets.
Stage Gate
Current progress reflected on and decision made on best next steps and whether to progress to Work Package 3.
Success criteria:
- Justification and clear rationale for decision on Stage Gate.
Work Package 4 – Next Steps, Planning and Dissemination
Geoprint tested in the context of long-term energy planning and a roadmap developed as to how NGED can take forward the technical learning points from the project into normal practice.
Success criteria:
- Understand how the Geoprint can contribute under different scenarios for specific timeframes, considering distributed flexibility, local balancing, and community energy growth. This will take into consideration other planning scenarios including RESP and DFES.
- Develop a future roadmap on the development of the Geoprint connection
- Project findings, lessons learnt in a cohesive report.
- Dissemination webinar